Quigley Road Connector
2
Quigley Road Connector
Design Concept & Scope
  • Scoping
    Committee
    Consensus
  • February 12, 2004


3
Quigley Road Connector Purpose and Need
  • Economic Development


  • Reduce Congestion


  • Remove Truck Traffic From Local Streets


  • Provide Access to the Cuyahoga Valley
4
Quigley Road Connector Engineering Design Considerations
  • Connects I-71/SR 174 and W. 14th St with Quigley Avenue to Clark Ave.
  • 3,500 feet long, 100 ft change in elevation
  • 6% grades
  • Roundabout Intersection
  • Relocate I-71NB to W14th St. Ramp
  • Bike Trail Coordination
5
Quigley Road Connector
Plan View
6
Quigley Road Connector
Environmental Studies
  • Ecological – No Impacts


  • Cultural Resources – Level I Survey


  • Haz Waste Studies – Complete


  • Noise – One residence impacted,
  • W. 14th has reduced noise levels



7
Quigley Road Connector
Project Schedule
  • Project Start - November 2004
  • Engineering Study – Complete May 2005
  • Right of Way Acquisition – Summer-Fall 2005
  • Construction Documents – November 2005
  • Project Sale - December 2005
  • Begin Construction – January 2006
  • Project Opening – September 2006