- Scoping
Committee
Consensus
- February 12, 2004
|
|
3
|
- Economic Development
- Reduce Congestion
- Remove Truck Traffic From Local Streets
- Provide Access to the Cuyahoga Valley
|
|
4
|
- Connects I-71/SR 174 and W. 14th St with Quigley Avenue to Clark Ave.
- 3,500 feet long, 100 ft change in elevation
- 6% grades
- Roundabout Intersection
- Relocate I-71NB to W14th St. Ramp
- Bike Trail Coordination
|
|
5
|
|
|
6
|
- Ecological – No Impacts
- Cultural Resources – Level I Survey
- Haz Waste Studies – Complete
- Noise – One residence impacted,
- W. 14th has reduced noise levels
|
|
7
|
- Project Start - November 2004
- Engineering Study – Complete May 2005
- Right of Way Acquisition – Summer-Fall 2005
- Construction Documents – November 2005
- Project Sale - December 2005
- Begin Construction – January 2006
- Project Opening – September 2006
|