Notes
Slide Show
Outline
1
INTRO
2
WELCOME
  • Meeting Format


  • Presentation Approach


  • Comment Form Importance/Deadline


  • Speaker Introductions
3
PROJECT HISTORY
  • December 17, 2004, Cleveland City Planning Commission adopted “Connecting Cleveland: The Waterfront District Plan”


  • The Lakefront West Project was initiated as a result of the Waterfront District Plan.
  • Plan calls for the removal of the limited access West Shoreway, replacing it with a calmer, pedestrian friendly facility that will allow the neighborhood connection to the lakefront
4
WEST SHOREWAY
5
PHOTOS
6
AERIAL PHOTO
7
POTENTIAL AERIAL
8
LAKEFRONT PLAN
9
PROJECT INTRODUCTION
  • PROJECT CORRIDOR: SR 2/USR 6/20


  • PROJECT LIMITS: Lake Avenue/West Boulevard on
    the west to the Main Avenue Bridge on the east


  • BUDGET: $40 Million available for construction of all portions of the project




10
PROJECT INTRODUCTION
11
PROJECT DEVELOPMENT PROCESS
  • PERFORM ENVIRONMENTAL ANALYSIS AND PRELIMINARY ENGINEERING
  •  Notify Property Owners
  •  Complete topographic field survey
  •  Prepare and submit Minor Project Preliminary Engineering Study
  •  Conduct first constructability review
  •  Identify existing utilities and coordinate with utility companies
  •  Prepare draft Categorical Exclusion (CE)
  •  Complete Waterway Permit determinations and draft applications
  •  Develop scope of services for final plan development (Concurrence
        Point #2)
  •  Update Project cost estimates


12
PROJECT DEVELOPMENT PROCESS
  • Identify Possible Access Point Locations – COMPLETED


  • Develop a Wide Range of Improvement Options for Each Access Point – TONIGHT’S PRESENTATION


  • Refine the range of Access Point Options based on project goals


  • Develop Corridor Alternatives that Incorporate Access Point Options


  • Identify the Preferred Corridor Alternative and submit the Draft Environmental Document


  • Submit the Final Environmental Document




13
PROJECT DEVELOPMENT PROCESS
  • Subcommittee Meetings (4 more meetings to be held)
  • Special Purpose Meetings (as needed)


  • Public Meetings (2 more meetings to be held)


  • Informational Mailings (as needed)


  • Project Website
    www.innerbelt.org/LakefrontWest/Lakefronthome.htm
14
PROJECT DEVELOPMENT PROCESS
15
PROJECT DEVELOPMENT PROCESS
  • To share the needs and challenges of the community segments that they represent with the Project Team


  • To share project information with their respective community segments


  • To work together to assist ODOT with solutions that balance the various interests of the entire community
16
PROJECT DETAILS
  • Improve Connectivity for Pedestrians, Bicycles, Vehicles and Trucks
  • Improve Access to Transit


  • Improve Parkland/Green Space


  • Eliminate Excess Infrastructure


  • Improve Development Potential


  • Public Involvement/Local Preference
17
PROJECT DETAILS
18
PROJECT DETAILS
  • West Boulevard/Lake Avenue
  • Clifton Boulevard/Lake Avenue


  • West 76th Street (Pedestrian/Bike only)


  • Father Caruso Drive (W. 73rd St.)
  • Father Caruso Drive (W. 65th St.)


  • Edgewater Park


  • West 54th Street


  • West 49th Street/West 45th Street


  • West 28th Street/West 25th Street
19
PROJECT DETAILS
20
AERIAL WEST/LAKE/CLIFTON
21
WEST/LAKE/CLIFTON NO BUILD
22
WEST/LAKE/CLIFTON OPTION B
23
WEST/LAKE/CLIFTON OPTION C
24
WEST/LAKE/CLIFTON OPTION D
25
WEST/LAKE/CLIFTON EVAL MATRIX
26
AERIAL W.76TH ST.
27
W. 76TH ST. NO BUILD
28
W. 76TH ST. OPTION A
29
W. 76TH ST. OPTION B
30
W. 76TH ST. EVAL AMTRIX
31
W.73RD/FATHER CARUSO AERIAL
32
W.73RD/FATHER CARUSO NO BUILD
33
W.73RD/FATHER CARUSO OPTION A
34
W.73RD/FATHER CARUSO GRADE
35
W.73RD/FATHER CARUSO  PHOTOS
36
W.73RD/FATHER CARUSO OPTION B
37
W.73RD/FATHER CARUSO GRADE
38
W.73RD/FATHER CARUSO EVAL MATRIX
39
W. 65TH ST./FATHER CARUSO AERIAL
40
W. 65TH ST./FATHER CARUSO NO BUILD
41
W. 65TH ST./FATHER CARUSO OPTION A
42
W. 65TH ST./FATHER CARUSO GRADE
43
W. 65TH ST./FATHER CARUSO OPTION B
44
W. 65TH ST./FATHER CARUSO GRADE
45
W. 65TH ST./FATHER CARUSO MATRIX
46
EDGEWATER PARK AERIAL
47
EDGEWATER PARK NO BUILD
48
EDGEWATER PARK OPTION A
49
EDGEWATER PARK OPTION B
50
EDGEWATER PARK OPTION C
51
EDGEWATER PARK MATRIX
52
W. 54TH ST. AERIAL
53
W. 54TH ST. NO BUILD
54
W. 54TH ST. OPTION A
55
W. 54TH ST. OPTION B
56
W. 54TH ST. OPTION C
57
W. 54TH ST. EVAL MATRIX
58
W. 49TH/W.45TH ST. AERIAL
59
W. 49TH/W.45TH ST. NO BUILD
60
W. 49TH/W.45TH ST. OPTION A
61
W. 49TH/W.45TH ST. OPTION B
62
W. 49TH/W.45TH ST. EVAL MATRIX
63
W. 28TH/25TH ST. AERIAL
64
W. 28TH/25TH ST. NO BUILD
65
W. 28TH/25TH ST. OPTION A
66
W. 28TH/25TH ST. OPTION B
67
W. 28TH/25TH ST. OPTION C
68
W. 28TH/25TH ST. OPTION D
69
W. 28TH/25TH ST. OPTION E
70
W. 28TH/25TH ST. OPTION F
71
W. 28TH/25TH ST. OPTION G
72
W. 28TH/25TH ST. OPTION H
73
W. 28TH/25TH ST. PLATE GIRDER
74
W. 28TH/25TH ST. TRUSS
75
W. 28TH/25TH ST. OPTION I
76
W. 28TH/25TH ST. OPTION J
77
W. 28TH/25TH ST. OPTION K
78
W. 28TH/25TH ST. EVAL MATRIX
79
WHAT’S NEXT?

  • Conduct Public Meeting #2 – Fall 2006 – to Present and Gather Input on the Corridor Alternatives


  • Conduct Public Meeting #3 – Winter 2006/2007 – to Present and Gather Input on the Preferred Corridor Alternative


  • To provide comments at anytime, visit the project website:
    www.innerbelt.org/Lakefrontwest/Lakefronthome.htm
80
THANK YOU
81
TODAY’S SPEAKERS

  • CRAIG HEBEBRAND
  • Ohio Department of Transportation
  • Cleveland Urban Core Projects Project Manager


  • ROBERT BROWN
  • City of Cleveland Planning


  • KIRSTEN BOWEN
  • Michael Baker Jr., Inc.


  • KEN RICH
  • McCormick Taylor, Inc.